Client: Merthyr Tydfil Council.
Project Descriptions: New car parking for office block.
Dates: 2017.
Project Work Types: Earthworks, Drainage, Footpaths, Kerbing, Roads construction, Ducting.
Project Value: £100k
Project Delivery: In house resources, Final surfacing subcontract.
Project Specialities: Material Management – cut & fill on earthworks, recycled aggregates.
Environmental: Working close to trees, site boundary acts as tree protection zone.
Value Engineering: Minimal muck away.
Client Feedback: Neat looking job, very good workmanship on the kerbing.
Client: Welsh Government / Costain / McCarthy.
Project Description: Improvements to junction 28 of the M4.
Date: Sept 2017 to Nov 2018.
Project Work Types: Earthworks, Drainage, Footpaths, Paving, Kerbing, Ducting, Finishes.
Project Value: £950k
Project Delivery: In house resources.
Project Specialities: Working with live traffic and a phased construction.
Environmental: Dust and silt management.
Value Engineering: Managing the programme to ensure each phase was completed in a timely manner.
Client Feedback: “I am delighted to mark the completion of this £13.7million construction project that will not only boost traffic flow but also improve road safety in the area.” Ken Skates – Minister for Economy and Transport.
Client: Rhonda Cynon Taff Council / Horan.
Project Description: Drainage improvement works within the Highway.
Date: Dec 2019 to Jan 2020.
Project Work Types: Drainage, Highway Reinstatement, Traffic Management.
Project Value: £75k
Project Delivery: In house resources, Final surfacing subcontract.
Project Specialities: Working with live traffic and a phased construction.
Environmental: Dust and silt management.
Value Engineering: Recycling the tarmac and old subbase for reuse.
Client Feedback: Pleased with the outcome and the professionalism of the team.
Client: Intelle Construction.
Project Description: Secant pile wall and capping beam to support the highway masonry wall.
Dates: Start June 2020 – ongoing.
Project Work Types: Pile cropping, RC works, retaining walls, Earthworks.
Project Value: £100k
Project Delivery: In house resources, Piling subcontract.
Project Specialities: Small site with minimal operating space.
Environmental: Managing noise levels for the local community.
Value Engineering: All works completed from the rear of the wall to minimise disturbance to the highway A4119.
Client Feedback: Greatly assisted the Site Manger with forward thinking and planning, the weekly programmes helped complete the first phase early.